Work System Design

Productivity, OEE, process capability, and SOPs - engineering the work itself, not just the workstation.

This is classical Industrial Engineering: time-and-motion study, line balancing, and equipment effectiveness. It's also where my published productivity work sits - the MOST-based engine assembly line study on my CV started here.

Hands-on Tools

Design and measure the work system

⚡ Live OEE calculation

OEE Calculator

Equipment Effectiveness

Overall Equipment Effectiveness = Availability × Performance × Quality.

Enter values and calculate.
⏱ Standard time chain

Standard Time Calculator

Time & Motion Study

Observed time → Normal time → Standard time, the core time-study chain behind MOST-based standards.

Enter values and calculate.
⚙️ Min-station line balance

Assembly Line Balancing

Line Balancing

Enter task times (comma-separated, in seconds/minutes) and the desired cycle time to get the minimum number of workstations and resulting balance efficiency.

Enter task times and cycle time.

Case Study

Engine Assembly Line Productivity (MOST)

The full DMAIC walkthrough of this study lives on the Lean Six Sigma page - summarized here from a Work System Design angle.

Journal · Communicated

Productivity Improvement of an Engine Assembly Line Using MOST

R. Saranraj and Dr. T. Ramesh Babu

Station-wise cycle times were decomposed into elemental motions using the Maynard Operation Sequence Technique (MOST), establishing standard times used to rebalance the line against takt time and reduce bottleneck-driven idle time.

Method: MOST, line balancing